2 Project
Description.. 1
2.1 Project
Location and Site History.. 1
2.2 Project Scope and Scale. 1
2.3 Implementation Programme. 4
2.4 Need and Benefit of the Project. 4
2.5 Consideration of Alternatives. 6
2.6 Interfacing and Concurrent Projects. 13
2.7 Documentation of Public Concerns. 15
List of tables
Table 2.1..... Existing
Effluent Standards of TPSTW to be Maintained for this Project. 2-1
Table 2.2..... Sewage Sludge and
Pre-treated Food Waste Co-digested under this Project. 2-2
Table 2.3..... Reclaimed Water Requirements
– WSD Water Quality Objectives. 2-3
Table 2.4..... Reuse of Treated Sewage
Effluent. 2-3
Table 2.5..... Environmental Benefits and Dis-benefits
of Alternative Sewage Treatment Schemes. 2-7
Table 2.6 .... Consideration of Treatment
Technologies for the Project. 2-7
Table 2.7..... Environmental Benefits and
Dis-benefits of Emergency Outfall Options. 2-11
Table 2.8..... Environmental Benefits and
Dis-benefits of Alternative Construction Sequences. 2-11
Table 2.9..... Environmental Benefits and
Dis-benefits of Alternative Demolition Methods. 2-13
Table 2.10... Environmental Benefits and
Dis-benefits of Alternative Piling Methods. 2-14
List of EXHIBITS
Exhibit
2.1 Water Depth and Fisheries Production
List of Figures
Figure
2.1... General Layout of TPSTW
Upgrading
Figure
2.2... Concurrent Projects
List of Appendices
Appendix 2.1 Existing Layout of Project Site
Appendix 2.2 Responses to Public Comments
2.1.1
The
Project site, covering the existing Tai Po Sewage Treatment Works (TPSTW) and
the proposed expansion site, is located in Tai Po
Industrial Estate (TPIE). TPIE is situated
on a flat reclaimed land and is surrounded by gentle hills to the North and
marine water to the South. The existing
Project site is bounded by industrial premises to the North, South and West and
Shuen Wan Restored Landfill (SWRL) to the East.
The TPIE (including the Project site) was once part of the Tolo Harbour
(i.e. the sea), and was formed via land reclamation
during the 1970s.
2.1.2
The
existing TPSTW comprises two independent plants, namely West Plant (Stage I/II)
commissioned in 1979/1983 and East Plant (Stage IV) commissioned in 1996. In order to cope
with the rapid development in the district, Stage V works were carried out to
further increase treatment capacity of TPSTW.
The Stage V works were completed in 2013. According to the information from DSD, there
is no TPSTW Stage III. The existing
design capacity of the West Plant and the East Plant is 44,000 m3 per day and 76,000 m3 per day respectively. The overall design
capacity of the existing TPSTW is therefore 120,000 m3 per day.
2.1.3
Currently, the proposed
expansion site (located on government land) comprises three Short Term
Tenancies (STTs) , a Temporary Government Land
Allocation (TGLA) lot and a vacant land.
The three STT lots have been utilizing by a number of
existing and past waste recyclers since lands were formed via reclamation. The existing or past land uses in the TGLA lot and the vacant land solely involve government’s and
contractors’ offices.
2.1.4
The general layout of the
existing facilities within the Project site is shown in Appendix 2.1.
Sewage Treatment Scheme
Design Capacity
2.2.1
This Project will upgrade the
design capacity of TPSTW from 120,000 m3 per day to 160,000 m3 per day to meet the projected
sewage treatment demand.
Treatment Level and Effluent Standards
2.2.2
The existing TPSTW provides
secondary level treatment of sewage with disinfection. The existing treatment level and treated
effluent standards of TPSTW will be maintained for this Project as summarized in
Table 2.1.
Table 2.1 Existing
Effluent Standards of TPSTW to be Maintained for this Project
Parameter
|
Unit
|
95th
percentile
|
Maximum
|
Annual
Average
|
Monthly
Geometric Mean
|
5-day Biological Oxygen
Demand (BOD5)
|
mg/L
|
20
|
40
|
-
|
-
|
Total Suspended Solids
(TSS)
|
mg/L
|
30
|
60
|
-
|
-
|
Total Nitrogen (TN)
|
mg/L
|
-
|
35
|
20
|
-
|
Ammonia Nitrogen (NH3-N)
|
mg/L
|
-
|
10
|
5
|
-
|
E. coli
|
counts/ 100mL
|
15,000
|
-
|
-
|
1,000
|
Effluent Disposal Scheme
2.2.3
Currently, the ultraviolet (UV)
disinfected secondary effluent from the existing TPSTW is discharged to Tolo Harbour
Effluent Export Scheme (THEES) for disposal in Victoria Harbour. During the
THEES maintenance period or under emergency situation,
the TPSTW effluent will be discharged via the existing emergency outfall of
TPSTW at the seawall of TPIE waterfront. This Project will follow the same
effluent disposal arrangement of the existing TPSTW during both construction
and operational phases.
Co-digestion of Sewage Sludge and Pre-treated
Food Waste
2.2.4
Sludge treatment facilities at
the existing TPSTW includes primary sludge gravity thickeners, surplus
activated sewage sludge thickening house, anaerobic digesters, sludge
dewatering works, and combined heat and power (CHP) units. The CHP units are used to recover energy from
the biogas generated in anaerobic digestion process for on-site electricity
supply.
2.2.5
The Environmental Protection
Department (EPD) will be responsible for the construction and operation of a
full-scale Organic Waste Pre-treatment Centre (OWPC) (New Territories East)
located adjoining to the northern boundary of TPSTW. The proposed OWPC will be designed to receive
and pre-treat organic waste or source-separated food waste of up to about 500
wet tonnes per day (wt/d), which is equivalent to about 75 dry tonnes per day
(dt/d).
2.2.6
The proposed anaerobic
co-digestion system of this Project will utilize sewage sludge from TPSTW,
other STWs in New Territories, and pre-treated food waste from the adjoining
OWPC. The pre-treated food waste will be
delivered from the OWPC to the adjacent TPSTW through enclosed pipelines. The sewage sludge from other STWs will be
dewatered before importing into the Project site by trucks. Total quantities of
sludge and food waste feedstocks to be managed under this Project are summarized in Table 2.2.
Table 2.2 Sewage Sludge and Pre-treated Food Waste
Co-digested under this Project
Type of Feedstock
|
Source of Feedstock
|
Quantity (dt/d)
|
Wastewater Derived Sewage
Sludge
|
TPSTW
|
35
|
Other existing and proposed STWs in New Territories
|
150
|
Pre-treated Food Waste
|
Proposed OWPC
|
75
|
Total
|
260
|
2.2.7
The energy generated from the proposed
co-digestion of sewage sludge and pre-treated food waste of the Project will be
utilized for electricity supply onsite. Any surplus electricity and / or gas
generated under this Project may be supplied to other government facilities
such as the adjoining OWPC as well as private companies such as the CLP Power
Hong Kong Limited and Hong Kong China Gas Company Limited.
Treated Sewage Effluent Reuse for Non-potable
Use
2.2.9
The reclaimed water will be
applied within the Project site for non-potable use such as toilet flushing and
landscape irrigation.
Table 2.3 Reclaimed
Water Requirements – WSD Water Quality Objectives
Parameter
|
Unit
|
Reclaimed Water Quality
|
E. coli
|
cfu/100mL
|
Non
detectable
|
Total Residual Chlorine
|
mg/L
|
≥1 (existing
treatment system)
|
Dissolved Oxygen (DO)
|
mg/L
|
≥2
|
TSS
|
mg/L
|
≤5
|
Colour
|
Hazen Unit (HU)
|
≤20
|
Turbidity
|
NTU
|
≤5
|
pH
|
-
|
6 to 9
|
Odour
|
Threshold odour no.
|
≤100
|
BOD5
|
mg/L
|
≤10
|
NH3-N
|
mg/L as N
|
≤1
|
Synthetic Detergents
|
mg/L
|
≤5
|
2.2.10
Some of the TSE (secondary effluent)
will be directly reused in the sewage treatment process (e.g.
for polymer preparation) within the Project site. Partially treated sewage,
including but not limited to surplus activated sludge (SAS), supernatant from
thickened SAS, primary effluent from the Project, may also be explored for
directly reuse in the treatment process (e.g. for
imported sludge dilution) within the Project site.
2.2.11
Some of the TSE of the Project
will be transferred to the proposed OWPC directly for use in the food waste pre-treatment
process or dilution of food waste. The reuse of effluent generated from the
sewage treatment process proposed in OWPC is covered in this EIA.
2.2.12
All the TSE or partially
treated sewage to be reused in the treatment process of this Project and the proposed
OWPC will be conveyed and handled within an automatic close-loop system without
direct human contact. The spent reclaimed water (e.g.
from toilet flushing) will be transferred back to the treatment units of this
Project by fully enclosed pipelines for further treatment. No human health
concern will arise. A summary of the proposed
effluent reuse is given in the table below.
Table 2.4 Reuse
of Treated Sewage Effluent
Effluent Type
|
Effluent Source
|
Effluent Reuse Location
|
Effluent Usage
|
Reclaimed
water
|
Effluent reuse facility
within the Project site (Sections 2.2.8 and 2.2.9)
|
Project site
|
Non-potable
use (e.g. toilet flushing, irrigation)
|
Effluent generated from the
sewage treatment process
|
Secondary treatment
facility of this Project (Section 2.2.10)
|
Project site
|
Reuse in sewage treatment (e.g. polymer preparation)
|
Secondary treatment
facility of this Project (Section 2.2.11)
|
OWPC
|
Reuse in food waste
pre-treatment process or dilution of food waste
|
Primary treatment facility,
SAS, supernatant from thickened SAS of this Project (Section 2.2.10)
|
Project site
|
Reuse in co-digestion (e.g. imported sludge dilution)
|
Construction Arrangement
2.2.13
In order to maintain normal sewage
treatment services of the existing TPSTW during the construction phase, a New
West Plant will be built in the proposed expansion site outside the existing
TPSTW boundary. The New West Plant will
be a relatively compact sewage treatment works (STW) and able to provide
adequate sewage treatment capacity to meet the projected sewage flow buildup
before the normal treatment services of the existing West Plant is
decommissioned.
Project Facilities and General Layout
2.2.16
The New West Plant of this
Project in the proposed expansion site will comprise inlet works, primary and
secondary treatment facilities and other ancillary works.
2.2.17
New sludge treatment and
co-digestion facilities will be located in the
existing TPSTW site. These facilities will include the import sludge reception
facilities, anaerobic digesters, sludge dewatering facilities, sludge
thickening facilities, biogas recovery and storage facilities, CHP units,
sidestream treatment facilities and other ancillary works. Expansion of the existing Tai Po Effluent
Pumping Station (TPEPS) will also be carried out within the existing TPSTW
site.
2.2.18
This Project will not involve
building higher than three storeys above ground level. All new facilities of
this Project are low-rise with building height similar to
the nearby existing industrial development in TPIE. The general Project layout
developed with reference to the preliminary design of this Project is shown in Figure 2.1.
2.3.1
The construction works of this
Project are tentatively scheduled to commence in 2025 for completion in
2036. Majority of the demolition works
in the existing West Plant of TPSTW will be carried out from 2029 to 2033 after
the New West Plant in the proposed expansion site is in operation.
Sewage Flow Projection
2.4.1
The flow projection for TPSTW
was evaluated with reference to the 2019-based Territorial Population and
Employment Data Matrix (TPEDM) data published in December2021, the latest
information of the proposed development projects within the sewerage catchment
area of TPSTW, historical TPSTW flow data, and EPD’s “Guideline for Estimating
Sewage Flows for Sewage Infrastructure Planning” (GESF, 2005).
2.4.2
The projected Average Dry
Weather Flow (ADWF) for the TPSTW catchment will nearly reach the existing
design capacity by 2031. Taking into account the
latest planning data, housing development programme, industrial flow, the
wastewater flows from sludge thickening, sludge dewatering, and co-digestion of
imported sewage sludge and pre-treated food waste, the required design ADWF for
the TPSTW may reach 160,000 m3 per day by 2041. Thus, there is a need to upgrade the capacity
of TPSTW to meet the required sewage treatment demand.
Aging of West Plant
2.4.3
The existing West Plant was
commissioned in 1979/1983 and has been in operation for nearly 40 years. Continuous aging of the existing West Plant
is expected, and this may result in increasing maintenance needs and demand for
substantial rehabilitation and modernization of the plant. This Project will provide an opportunity to
develop a New West Plant with improved sewage treatment technologies and
efficiency, minimizing the possibility of emergency sewage discharge, and
release of odour due to equipment failure.
Synergy of Sewage Sludge and Organic Waste
Co-digestion
2.4.4
The upgrading of TPSTW provides
opportunity to co-digest indigenous sewage sludge from TPSTW, imported sewage
sludge from multiple STWs in New Territories and imported pre-treated food
waste from the proposed OWPC adjacent to TPSTW.
There will be a synergy effect in co-location and co-treatment of
different waste types in TPSTW.
2.4.5
The anaerobic co-digestion of
sewage sludge and pre-treated food waste will improve nutrient balance and
biogas yield, and thus increase energy recovery from the anaerobic digestion
process.
Preservation of Landfill Space
2.4.6
The Project will facilitate the
recycling of up to 260 dt/d of sewage sludge and pre-treated food waste, contributing
to the preservation of precious landfill space and reduction of landfill gas
including methane generated at landfills.
Minimization of Environmental Impact
2.4.7
Provision of adequate STW
capacity to cope with new development and population growth will be essential
for protection of coastal water quality. This Project is thus beneficial to the
environment by reducing the pollution loading and avoiding the release of
untreated sewage from other new developments.
This Project will also reuse the TSE for non-potable use, resulting a
further positive environmental effect by minimizing the TSE discharge and
pollution loading to the water environment.
Comparison between With and Without
Co-digestion
2.4.8
Previous studies concluded that
provision of dedicated organic (food) waste treatment facilities (i.e. organic resources recovery centre (ORRC)) and
implementation of sewage and food waste co-digestion at STW are both
economically viable and comparable.
2.4.9
Further to the commissioning of
ORRC at Siu Ho Wan (O·Park1) and the ongoing construction of O·Park2 at Sha
Ling, the Government extend the spectrum of resource recovery and divert food
waste from landfill through the implementation of co-digestion at STW.
2.4.10
Based on the findings of
“Agreement No. CE 55/2015 (EP) A Review of the Management and Disposal
Arrangement for Sewage Sludge – Feasibility Study”, it is viable and beneficial
to implement co-digestion facilities within TPSTW for the treatment of
indigenous sewage sludge, imported sewage sludge, and 500 wt/d of food waste
from the OWPC, which would bring forth the synergy in biogas production and
utilisation at the TPSTW, at the same time, converting food waste into
renewable energy.
2.4.11
Without co-digestion, the
Project contribution to the sustainability and circularity for waste management
in Hong Kong will be lost.
Scenario without the Project
2.4.12
The capacity of the existing
TPSTW will be inadequate to cope with the increase in sewage flow within its
catchment in the coming years. The possible consequences of not implementing
this Project will include the discharge of untreated sewage into the Tolo
Harbour or the need for an alternative sewage treatment scheme to handle the
excess flow. The benefits associated with co-digestion as described in Section
2.4.9 to 2.4.11 will be lost. In particular, more landfill space will be occupied and additional land will be required for
construction of new ORRC.
Scenario with the Project
2.4.13
With the Project, the treatment
capacity of TPSTW will be upgraded to meet the projected sewage treatment
demand in its sewage catchment areas. Thus, the coastal water quality can be
protected by avoiding the release of untreated sewage into the Tolo Harbour
from other new developments.
2.4.14
Implementation of this Project
will provide opportunity to improve odour management in the TPSTW by replacing
the existing open surface sewage treatment units, which are major odourous
sources, in the West Plant, with new treatment units equipped with odour covers
and deodourisation systems. With implementation of this Project, an improvement
of the existing odour environment in TPSTW is anticipated.
Alternative Project Sites
2.5.1
Due
to the space constraints, upgrading within the existing TPSTW site will require
demolition of existing treatment units before construction of new Project
facilities. As the existing TPSTW is already operating close to its design
capacity, terminating part of the existing facilities within TPSTW for expansion
will likely induce bypass of untreated sewage or partially treated effluent
failing to meet the discharge standards.
Upgrading within the existing TPSTW site only is not a feasible option.
2.5.2
Utilizing
the proposed expansion site adjoining the existing TPSTW is recommended for the
Project. It is a government land where
the existing land uses (STTs and TGLAs) are temporary. The land can be utilized
for construction of new Project facilities prior to decommissioning of the
existing facilities in TPSTW. This
option is selected for the Project as it will cause minimal interruption to the
normal treatment services during both construction and operational phases (see
Sections 2.2.13 to 2.2.14 above).
2.5.3
By
virtue of its upgrading and co-locating natures, except the adjoining expansion site,
no other alternative site location is applicable to this Project.
Alternative Sewage Treatment Schemes
2.5.4
The
existing TPSTW provides a secondary level treatment. Tolo Harbour is rich in
fisheries resources including four existing Fish Culture Zones (FCZs) and an important nursery area of commercial fisheries resources. To resolve the
red-tide problem in Tolo Harbour, which may cause fish kills and adverse impact
on marine life, the disinfected secondary effluent from TPSTW has been
transferring to Victoria Harbour for discharge since the THEES implementation
in the 80s. The water quality in Tolo
Harbour has shown marked improvement in the past three decades.
2.5.5
Kai
Tak River is the receiving water of the THEES effluent. It is a man-made concrete nullah in highly
developed urban land for drainage purpose. It is designed to receive treated
sewage effluent from THEES and stormwater from a large catchment of old
urbanized areas. There has been no
report of any particular environmental concern in
Victoria Harbour due to the treated effluent discharge from the THEES. Based on the past records and the water
quality impact assessment in Section 4, the THEES effluent will not affect the
open channel of Victoria Harbour with high flushing capacity. It is concluded that the secondary level
treatment will be the most effective treatment level for the Project in
minimizing the water quality impacts in Victoria Harbour.
2.5.6
Two
sewage treatment schemes have been considered for the Project as follows.
Existing Treatment Level for Discharging to the Victoria Harbour
(Recommended Option)
2.5.7
This
option will require the THEES system to accommodate the additional flow of 40,000 m3 per day (i.e. increase from 120,000 m3 per day to 160,000 m3 per day). The Project may remain as a
secondary treatment works without any change to the water quality discharge
standards.
Tertiary Treatment for Discharging to the Tolo Harbour
2.5.8
This
will require construction and operation of a new tertiary treatment plant for
discharging the additional flow of 40,000 m3 per day to Tolo Harbour. The remaining
TPSTW secondary effluent will be discharged to the THEES for disposal. Despite
the reduced contaminant concentration in the tertiary effluent, this option
will permanently increase the pollution load to the sensitive Tolo Harbour,
which is not preferred.
2.5.9
The
environmental benefits and dis-benefits of the alternative treatment schemes
are summarized as follows.
Table 2.5 Environmental
Benefits and Dis-benefits of Alternative Sewage Treatment Schemes
Options
|
Environmental Benefits
|
Environmental Dis-benefits
|
Existing Treatment Level for Discharging to the
Victoria Harbour (Recommended Option)
|
n No additional
discharge to Tolo Harbour
n Protection of
water quality, fisheries and ecological resources in
Tolo Harbour
|
n Additional
discharge and potential water quality impact in Victoria Harbour, which has
been assessed under this EIA to be acceptable (see Section 4).
|
Tertiary
Treatment for Discharging to the Tolo Harbour
|
n No additional
discharge and no water quality impact in Victoria Harbour
|
n Permanent discharge
and potential water quality impact in the sensitive Tolo Harbour
|
Alternative Treatment Technologies
2.5.10
Consideration of alternative
sewage treatment technologies for the Project is summarized below.
Table 2.6 Consideration
of Treatment Technologies for the Project
Category
|
Technology
|
To
Be Considered In Design Stage
|
Comments/Notes
|
Primary Treatment
|
Conventional Sedimentation/
Clarification
|
X
|
Eliminated as the Project site does not
have sufficient space to accommodate the facilities
|
Ballasted Flocculation
|
X
|
Eliminated as the Project site does not
have sufficient space to accommodate the facilities
|
High Rate
Filtration (HRF)
|
√
|
|
Mechanical Mesh Filter (MMF)
|
X
|
Eliminated because it was shown to be
less space efficient than HRF
|
Biological Active Filter (BAF)
|
X
|
Eliminated because high TSS in raw
sewage may lead to frequent clogging of the filters
|
High Rate
Lamella Clarification
|
X
|
Eliminated due to high chemical
consumption (ferric, polymer, carbon source) and release of residual
chemicals, which may affect the downstream biological treatment
|
Lamella Plates Sedimentation (LPS)
|
√
|
|
Secondary Treatment
|
Aerobic Granular Sludge (AGS)
|
√
|
|
Membrane Bioreactor (MBR)
|
√
|
|
Moving Bed Biofilm Reactor – Dissolved
Air Flotation (MBBR-DAF)
|
√
|
|
Membrane Aerated Biofilm Reactor (MABR)
|
X
|
Eliminated as the Project site does not
have sufficient space to accommodate the facilities
|
Biological Active Filter (BAF)
|
X
|
Eliminated as the Project site does not
have sufficient space to accommodate the facilities
|
Integrated Fixed-Film Activated Sludge
(IFAS)-Secondary Clarifier
|
X
|
Eliminated as the Project site does not
have sufficient space to accommodate the facilities
|
Sludge Treatment
Technologies
|
Conventional Mesophilic Anaerobic
Digestion (MAD)
|
√
|
|
Thermal Hydrolysis Process (THP) with
Anaerobic Digestion
|
√
|
|
Dewatering
Process Side-stream Nutrient Removal Technologies
|
Deammonification
|
√
|
|
Post Aerobic Digestion (PAD)
|
X
|
Eliminated due to the possible foaming
and production of malodorous air
|
2.5.11
The
available space at the proposed expansion site is limited. The results of treatment option evaluation
suggest that it is feasible and beneficial to implement the new West Plant in
the proposed expansion site using the HRF or LPS technology (for primary
treatment) as well as the AGS or MBR or MBBR technology (for secondary
treatment). These compact-type technologies (coupled with UV disinfection) will
provide secondary level treatment capable of achieving the proposed effluent
standards presented in Table 2.1.
2.5.12
The
treatment option evaluation also suggests that it is feasible to accommodate
the new co-digestion facilities within the existing TPSTW, which conventional
MAD with or without THP is recommended.
2.5.13
Deammonification
has been evaluated to be the preferred technology for removing the nutrient in
the liquid side stream from the sludge dewatering process (before the side
stream is returned to the main liquid treatment process).
2.5.14
Change
of the sludge treatment technologies may affect the biogas production rate. The
preliminary arrangement of biogas related facilities and storage volume assumed
in the hazard to life assessment of this EIA have been reviewed to be
applicable to the conventional MDA with or without THP. Other key environmental
impacts during the Project operation will be the air quality (odour) and
noise. Contemporary good practice is for
all odourous treatment units to be enclosed, and
having the exhaust air treated to remove odour emissions to an acceptable
level. The enclosed nature of the new
West Plant and the new co-digestion facilities will also help mitigating the
noise impact.
2.5.15
In
summary, the acceptability of environmental impacts arising from the Project is
not sensitive to the choice of treatment technology to be considered in the
design stage. The environmental benefits
and dis-benefits of different treatment technologies are not further
considered.
Alternative Emergency Outfall Options
2.5.16
Under normal operation, treated sewage effluent from the Project will be
conveyed by the THEES effluent tunnel for discharge into Victoria Harbour. An emergency outfall is needed for bypass of treated or partially treated effluent to Tolo Harbour during the THEES maintenance period or emergency situations. Two options
of an emergency outfall for the Project have been considered as discussed
below.
Utilization of the Existing Emergency Outfall (Recommended Option)
2.5.17
The existing emergency outfall
of TPSTW is in the form of underground sewage pipeline for diverting the
effluent from TPEPS for discharge at the seawall to the south of Tai Po
Industrial Estate (TPIE). The existing sewage pipeline has been reviewed to have sufficient
capacity to handle the design flow of this Project. The marine water depth to
the south of the existing emergency outfall or close to the waterfront of TPIE
is > 2 - 5 m below the Chart Datum (mCD).
Although the water depth near the outfall is relatively shallow, which
may not be favorable to effluent dispersion, it is located in
an area with the lowest fisheries production yield amongst all other waters in
Tolo Harbour. The fisheries production yield recorded near the outfall is
>50 -100 kg/ha.
Exhibit 2.1 Water Depth and Fisheries Production
Source
of Information:
Water
depth - Marine Department.
Fisheries
production – 2016 / 2017 Port Survey, Agriculture, Fisheries and Conservation
Department.
2.5.18
Using the existing emergency outfall for this Project is predicted to
cause no unacceptable water quality, ecological and fisheries impacts with the
implementation of the recommended mitigation measures (see Sections 4, 5 and
6). In order to minimize the scale and scope of construction and
the associated environmental impacts, construction of new emergency outfall is
not proposed.
Construction of a New Submarine Outfall
2.5.19
Diverting the effluent discharge to a deeper water away from the
coastline may enhance the effluent dispersion and dilution effect. In view that
the waters to the further south of the existing seawall outfall are also
relatively shallow with similar depths and in order to
achieve a better or noticeable dilution effect, the outfall should be extended
to a location beyond the contour line of 5 mCD in the east (as shown in Exhibit
2.1 above). However, such location
could be closer to the existing FCZ or area with higher fisheries production
yield. This option will also require the laying of new outfall diffuser in the
deeper water. Installation of the new outfall diffuser may disturb the seabed
sediments and cause a release of sediment and
sediment-bounded contaminants during the construction phase. The new outfall diffuser will also induce a
permanent loss of fishing ground in Tolo Harbour. This option is not further
considered.
2.5.20
The
environmental benefits and dis-benefits of the alternative emergency outfall
options are summarized as follows.
Table 2.7
Environmental Benefits and Dis-benefits of Emergency Outfall Options
Options
|
Environmental Benefits
|
Environmental Dis-benefits
|
Utilization of the Existing Emergency Outfall
(Recommended Option)
|
n No loss of fishing
ground nor marine habitat during construction and operational phases.
n No disturbance to
seabed sediment and no release of sediment-bound contaminants in Tolo
Harbour.
|
n Relatively poorer
effluent dispersion capacity in shallower water during operational phase.
n The water quality
impact, however, has been assessed to be acceptable with proper
implementation of the recommended mitigation measures (see Section 4).
|
Construction of a New Submarine Outfall
|
n Potentially better
effluent dispersion and dilution capacity in deeper water during operational
phase.
|
n Release of
sediments and sediment-bounded contaminants (e.g.
metals) during construction of new outfall diffuser and inducing additional
marine water quality, fisheries and marine ecological impacts.
n Temporary loss of
fishing ground in Tolo Harbour during the construction of the new outfall
diffuser.
n Permanent loss of
fishing ground and marine habitat due to operation of the new outfall
diffuser.
|
Alternative Construction Sequences
2.5.21
Two construction sequences have been considered for the Project as
follows.
Phased Construction (Recommended Option)
2.5.22
Phased construction as
described in Sections 2.2.13 and 2.2.14 will allow construction and commissioning of
new treatment units before the demolition of existing similar facilities such
that adequate treatment capacity can be provided through the construction
phase.
Concurrent Construction in Existing TPSTW and Proposed Expansion
Site
2.5.23
Due to the limited space available, construction of new facilities in
TPSTW will require prior decommissioning and demolition of existing facilities
in TPSTW. Under this option. construction in existing
TPSTW will be carried out prior to the completion and commissioning of the new
West Plant in the proposed expansion site.
Table 2.8 Environmental Benefits and Dis-benefits of
Alternative Construction Sequences
Options
|
Environmental Benefits
|
Environmental Dis-benefits
|
Phased
Construction (Recommended Option)
|
n This option will
maintain continuous sewage treatment services throughout the construction
phase and eliminate the chance of temporary sewage bypass into the
environment.
n Phased
construction will reduce the total construction emissions (dust and noise) at
one time and minimize the environmental impacts.
|
n This option may imply
a relative longer construction period. The overall duration of construction
phase impact on the environment may be lengthened.
|
Concurrent
Construction in Existing TPSTW and Proposed Expansion Site
|
n This option may
imply a relatively shorter construction period. The overall duration of
construction phase impact on the environment may be shortened.
|
n There will be a
higher chance to release untreated sewage effluent into the environment and
induce additional marine water quality, ecology and fisheries impacts in Tolo
Harbour.
n The cumulative or
total pollution emissions (dust and noise) at a time will be higher during
the construction phase.
|
Alternative
Demolition Methods
2.5.25
This Project will involve partial demolition of the existing treatment
units in TPSTW for construction of new facilities. Different demolition methods
have been considered and are discussed as follows.
Breakers Mounted on Excavator (Recommended Option)
2.5.26
Using breakers mounted on
excavator is a conventional method for demolition of all types of
structures. Concrete breaking using this
method will induce a relatively higher noise emission as compared to other
quieter methods.
2.5.27
Based on the construction programme
and due to the urgency to upgrade the TPSTW to cater for the projected sewage
flow buildup, the time allowing for the demolition works of this Project will
be limited. Demolition of key facilities
in the existing TPSTW cannot be carried out until the completion and
commissioning of the new West Plant of this Project to ensure normal sewage
treatment services throughout the construction phase. The demolition of the existing TPSTW will
also need to be undertaken by stages in order to maintain adequate sludge
treatment capacity throughout the construction phase (see Sections 2.2.13 and 2.2.14 above). Using breakers mounted on excavator
will be the most efficient scheme and a faster demolition method to meet the
tight construction programme.
2.5.28
There is no Noise Sensitive
Receivers (NSRs) identified within 300 m from the Project site. The planned NSRs (staff quarters, overnight
accommodations, etc.) of the proposed Shuen Wan Golf Course (SWGC) as
identified in the approved EIA for SWGC are all located outside the noise
impact assessment area of this EIA. According to the ecological impact
assessment in Section 5, the key pre-roosting/roosting sites of Collared Crow
and roosting sites of Black Kites in Shuen Wan Restored Landfill (which may be
sensitive to noise) are separated from the construction site of this Project.
Most of them are blocked by the existing topography with no direct line of
sight to the Project construction activities. It is recommended that movable
and non-reflective temporary noise barriers with sound absorptive materials can
be deployed close to noisy plant and be moved concurrently with the plant along
a worksite for effective noise screening from the pre-roosting sites located to
the east of the Project site. Quality Powered Mechanical Equipment (QPME)
listed in the QPME system in the EPD web pages will also be used as far as
possible.
2.5.29
An existing tree group located
within the proposed works area of this Project is identified as an occasional
night roosting habitat for the non-breeding ardeids. The concerned tree group
will be transplanted or compensated within the Project layout. To minimize the
disturbance (e.g. construction noise) to any roosting
ardeids, all noisy construction works within 100m of the concerned tree group
should cease at least 1 hour before sunset before the removal/transplantation
of the tree group. All noisy
construction works within 100m of the relevant transplantation/compensation
planting area should also cease at least 1 hour before sunset after
transplantation/compensatory planting.
2.5.30
No unacceptable noise impact
would be expected with implementation of the recommended mitigation measures.
Quieter Demolition Methods
2.5.31
Concrete breaking using quieter equipment such as
crushers and saw cutting can reduce the noise emissions as compared to the
breakers mounted on excavator. The
demolition rates of using these methods are generally longer. Using these
slower demolition methods will be infeasible to meet the construction programme
and are therefore not selected.
2.5.32
The
environmental benefits and dis-benefits of the alternative construction
sequences are summarized as follows.
Table 2.9
Environmental Benefits and Dis-benefits of Alternative Demolition Methods
Options
|
Environmental
Benefits
|
Environmental
Dis-benefits
|
Breaker Mounted on Excavator (Recommended Option)
|
n Shorter
demolition duration and shorter demolition noise emission period.
|
n This option will
induce a higher noise level in TPIE but no NSRs are identified in TPIE
|
Quieter Demolition Methods (such as using crushers
or saw cutting)
|
n These quieter
demolition methods may reduce the construction noise level in TPIE.
|
n Longer demolition
duration and longer demolition noise emission period.
|
Alternative Piling Methods
2.5.33
Piling will be required for
construction of the foundation for new facilities at the Project site.
Selection of the piling methods will be subject to the site-specific ground
conditions. Alternative piling methods have been considered as follows.
Quieter Piling Methods (Recommended Option)
2.5.34
Quieter piling method, namely
pre-bored steel H piles, will involve a hole (formed by rotary dill into the
ground and to the rock where the upper section in soil is supported by a steel
casing. The steel H piles are then inserted and grout
is pumped into the hole while the steel casing is removed. No percussive action
is required for forming the holes.
2.5.35
This method is not applicable
for all types of ground conditions. For example, it will require a longer
construction time in areas with a very deep bed rock.
2.5.36
Based on the preliminary Ground
Investigation (GI) data available at the Project site, this quiet piling method
is considered suitable. It is therefore proposed to use this method as far as
practicable to minimize the noise impact.
Percussive Piling (Alternative Option)
2.5.37
Construction of percussive
piles will induce a relatively high disturbance in term of noise level during
the construction stage. With this
consideration, application of percussive piling should be avoided as far as
practicable.
2.5.38
This method is applicable to
all ground conditions with less construction time required.
2.5.39
If any updated GI data (to be
collected at the design stage of this Project) reveal that the pre-bored steel
H piles are not practical, this conventional percussive pilling should be used
as an alternative method and should be undertaken within non-sensitive hours (e.g. close to noon) as far as practicable.
2.5.40
The
environmental benefits and dis-benefits of the alternative piling method are
summarized as follows.
Table 2.10
Environmental Benefits and Dis-benefits of Alternative Piling Methods
Options
|
Environmental Benefits
|
Environmental
Dis-benefits
|
Quieter Piling Methods (e.g.
pre-bored steel H piles) (Recommended Option)
|
This option will induce a lower level of noise
disturbance in TPIE.
|
|
Percussive Piling (Alternative Option)
|
|
This option will
induce a higher level of noise disturbance in TPIE
|
Other Construction Activities
2.5.41
Other Civil & Structural works including
the excavation and concrete construction works will be adopted for the Project.
Control of the total active construction works area at a time or phasing of
construction have been considered in the air quality impact assessment in
Section 3 to minimize the construction dust impact. For Electrical and
Mechanical (E&M) works, general fixing and installation of treatment plants
and facilities such as pumps and conveyors are required.
For Building Services works, small-scale utilities installations such as
pipe-laying, ducting and cabling will be
conducted. The E&M and Building
Services works are considered to create less environmental impact (dust and
noise emissions). It is recommended that construction by precast or
prefabrication units should be adopted as far as practicable to minimize the
environmental impacts during construction phase.
2.6.1
This section describes the
interfacing and concurrent projects based on the best available information at
the time of preparing this EIA Report. Locations of concurrent projects in the
vicinity of the Project site are presented in Figure 2.2. The description and
layout of these concurrent projects as presented below will be subject to
changes and further updates by the respective project proponents.
Proposed Sha Tin Cavern Sewage Treatment
Works
2.6.2
This is a DSD project, which
mainly include relocation of the existing Sha Tin Sewage Treatment works
(STSTW) to caverns. During normal plant operation, the effluent of the proposed
Sha Tin Cavern Sewage Treatment Works (CSTW) will be discharged to Kai Tak
River in Victoria Harbour via the Tolo Harbour Effluent Export Scheme (THEES).
The discharge of CSTW effluent into the Tolo Harbour will occur during the
THEES maintenance period or under emergency condition. The cumulative environmental impact due to
the concurrent discharge from the CSTW operation have been considered in this
EIA. The project is currently under construction phase and is anticipated to commission
before 2030. The construction activities
of the CSTW project is outside the assessment area of
this EIA.
Proposed THEES Upgrading
2.6.4
The proposed THEES upgrading
works involve expansion of the Tai Po Effluent Pumping Station (TPEPS) within
the Project site, as well as construction of a new effluent rising mains in TPIE
and a new submarine pipeline (across inner Tolo Harbour) to handle the Project
flow.
2.6.5
The new submarine pipeline will
be installed by the Horizontal Directional Drilling (HDD) method, which is a
trenchless method with no disturbance to the seabed and marine habitat. All the remaining THEES upgrading works are
land-based.
Proposed Shuen Wan Golf Course
2.6.7
The proposed Shuen Wan Golf
Course (SWGC) is located to the east of the Project site. It mainly involves
the development of a new golf course within the existing Shuen Wan Restored
Landfill (SWRL) site. According to the SWGC EIA Report, the construction of the
proposed SWGC would be completed in end 2023 prior to the construction of this
Project. Cumulative effects of the SWGC in particular on the terrestrial ecology have been
considered in this EIA.
Proposed Organic Waste Pre-treatment Centre
Planned Residential Development at Ting Kok
2.6.9
Construction and operation of
this land-based project will be located over 500m from the Project site. No
cumulative environmental impact will be expected from this residential
development project.
Kai Tak
Development – Interception and Pumping Scheme
2.6.10
A new Interception and Pumping (IP)
Scheme is being planned under the Kai Tak Development (KTD). The proposed IP
Scheme will involve new cooling water intakes at Kai Tak River (KTR) and Kai
Tak Approach Channel (KTAC). The water pumped from KTR and KTAC will be
diverted to the District Cooling System (DCS) for cooling purpose and all the
spent water will be discharged into the Kowloon Bay. The proposed IP scheme
will divert the water in the embayed areas of KTR and KTAC to the more open
water in Kowloon Bay and potentially improve the water circulation and water
quality in KTAC. The relevant environmental effect of this proposed IP scheme have been considered in this EIA.
2.7.1
Most of the public comments
received during the exhibition of the Project Profile under the EIAO process
are related to the potential impacts on Collared Crow with conservation
interest. As part of the EIA study, consultation with the Hong Kong Bird
Watching Society (HKBWS) was undertaken in 2022. Appendix 2.2 summarizes the main public
concerns raised on the Project and how the relevant concerns have been
addressed in the EIA study.